Well ahead of the original start date contractors started on the 8th February with the upstairs strip out. Ours is a Dorma Design House so bedrooms upstairs consists of plaster board attached to the roof rafters all now gone!
Fire damaged Purlings & Roof Trusses have been replaced with almost half the roof now covered in new roofing felt type stuff with batons ready for the tiles. Some of the fascia/soffits have been removed and replaced replaced with disposal of old asbestos parts.
All of the ground floor Porcelain tiles have been removed, all the Kitchen is now in a skip, rear bedroom floorboards gone as they are to be replaced.
Temporary power board connected to enable the dehumidifiers to be installed. Am hoping that the whole roof will be done within a couple of weeks provided weather does not hinder progress.
Fire damaged Purlings & Roof Trusses have been replaced with almost half the roof now covered in new roofing felt type stuff with batons ready for the tiles. Some of the fascia/soffits have been removed and replaced replaced with disposal of old asbestos parts.
All of the ground floor Porcelain tiles have been removed, all the Kitchen is now in a skip, rear bedroom floorboards gone as they are to be replaced.
Temporary power board connected to enable the dehumidifiers to be installed. Am hoping that the whole roof will be done within a couple of weeks provided weather does not hinder progress.