We had a site meeting yesterday with Contractors, our Loss Assessor & Insurance appointed Representative.
Our Practical Completion Date has pushed back a couple of weeks to the 26th June 2018.
We have a Snagging List meeting on the 15th June 2018 so if the list is short we might be able to move back in before the 26th.
We are very pleased with the quality of the work done so far, complete new roof is finished, all except the kitchen has been re-plastered with wash coat of paint for initial sealing. Floor tiling should be done by the end of this week leaving the Kitchen for last.
Lots still to do but real progress in the last two weeks. I will do some pictures at the weekend and post them.
Our Practical Completion Date has pushed back a couple of weeks to the 26th June 2018.
We have a Snagging List meeting on the 15th June 2018 so if the list is short we might be able to move back in before the 26th.
We are very pleased with the quality of the work done so far, complete new roof is finished, all except the kitchen has been re-plastered with wash coat of paint for initial sealing. Floor tiling should be done by the end of this week leaving the Kitchen for last.
Lots still to do but real progress in the last two weeks. I will do some pictures at the weekend and post them.